Please see below anticipated work (weather permitting) through March 25, 2022:

Pile driving east or west of the US 1 bridge to install the main bascule piers' foundations. Please anticipate heightened noise levels during daytime hours.

  • Installing traffic signal foundations on Alternate A1A and US 1.
  • Removing debris in the waterway. 
  • Partially removing the existing bridge's southwest and northwest bulkheads.
  • Concrete repairs to the Alternate A1A bridge over the Loxahatchee River.
  • Relocating utilities.


Traffic Impacts


  • The inside southbound shoulder of Old Dixie Highway to southbound Alternate A1A may be closed from 9 a.m. to 4 p.m. on Wednesday, March 9, to install traffic signal foundations.
  • Alternate A1A’s northbound right-turn lane between Old Dixie Highway and US 1 may be closed from 9 a.m. to 4 p.m. on Monday, March 14, to install traffic signal foundations.
  • US 1’s southbound outside lane and bike lane between Eyeball Avenue and Bridge Road may be closed from 9 a.m. to 4 p.m. on Tuesday, March 15, to install foundations for a digital message sign.
  • CR A1A’s westbound right-turn lane to northbound US 1 may be closed from 9 a.m. to 4 p.m. on Wednesday, March 16, to install traffic signal foundations.
  • Upcoming traffic switch: One outside lane in each direction is closed on the Alternate A1A bridge over the Loxahatchee River for concrete repairs. On the evening of Wednesday, March 16, the outside lanes will reopen and one inside lane in each direction will be closed continuously through April.


 For more information, please contact FDOT:

 Contact Information:

Angel Streeter Gardner
Community Outreach Specialist
(561) 886-8773
angel@valerin-group.com

Bodler Barthelemy, P.E.
FDOT Project Manager
(561) 370-1127
bodler.barthelemy@dot.state.fl.us

U.S. 1 Bridge Construction Updates