US 1 Bridge Update - January

News Release Date
01-08-2024
Back to News

US 1 JUPITER BRIDGE RECONSTRUCTION MONTHLY PROGRESS REPORT

Tuesday, January 2, 2024 marked day 807 of 1524, with 53% completed. The project is currently on schedule to open one lane in each direction by Fall 2024, with overall project completion anticipated in Spring 2026. Additional information and progress photos can be found on the project page.